Large Load Queue –Past 10 Months Changes since October LFLTF Meeting •ERCOT has removed some projects from the queue after conversations with TSPs identified projects that had been cancelled. 2 5,186 7,936 8,130 8,322 8,752 8,817 8,605 8,507 ... Current Large Load Interconnection Queue 3
Large load interconnections in the Electric Reliability Council of Texas (ERCOT) have been on the rise since 2021. These new players in the ERCOT market are most commonly: data centers, crypto mining facilities, and hydrogen production facilities (aka electrolyzers). Texas has attracted these large loads due to the abundance of affordable ...
Here, we investigate the potential for new wind and solar projects already proposed in the ERCOT interconnection queue as of June 2020 to replace the coal power that remained in 2019. The Wind …
Queued Up: Status and Drivers of Generator Interconnection …
The average time projects spent in queues before being built has increased markedly. The typical project built in 2022 took 5 years from the interconnection request to commercial operations1, compared to 3 years in 2015 and <2 years in 2008. 1. In-service date was only available for 58% of all operational projects.
Loads Approved to Energize – Observations. Of the 4,479 MW that have received Approval to Energize, ERCOT has observed a non-simultaneous peak consumption of 2,587 MW. This is calculated as the sum of the maximum value for each individual load regardless of when that maximum occurred. This value represents how …
Large Load Interconnection Status & Analytics Update
Loads Approved to Energize – Observations. Of the 4,479 MW that have received Approval to Energize, ERCOT has observed a non-simultaneous peak consumption of 2,844 MW. This is calculated as the sum of the maximum value for each individual load regardless of when that maximum occurred. This value represents how …
ERCOT''s Interconnection Queue: How quickly do batteries …
According to the May 2024 Generation Interconnection Status (GIS) report, more than 149 GW of battery energy storage is in the ERCOT Interconnection queue. This number has been growing rapidly, up from 103 GW just twelve months ago - a 45% increase in just one year. Every battery project in the queue that currently has a …
ERCOT is currently reviewing proposed transmission improvements with a total estimated cost of $533.54 Million as of October 31, 2022. Transmission Projects endorsed in 2022 total $2.565 Billion as of October 31, 2022. All projects (in engineering, routing, licensing and construction) total approximately $11.093 Billion as of October 1, …
Queued Up: Characteristics of Power Plants Seeking Transmission Interconnection …
Capacity in interconnection queues as of the end of 2023. *Hybrid storage capacity is estimated in some cases using storage: generator ratios from projects that provide separate capacity data. Storage capacity in hybrids was not estimated for years prior to 2020. ...
Interconnection Queue Capacity by Fuel Type Queue totals: Solar 123 GW (50.2%), Wind 24 GW (9 .7%), Gas 13 GW (5.3%), Battery 83 GW (33.7%) (Excludes capacity associated with projects designat ed as Inactive per Planning Guide Section 5.7.6) A break-out by zone can be found in the monthly Generator In terconnection Status …
Current Large Load Interconnection Queue. NOTE: In July 2023, ERCOT identified a database error that had caused some projects to be misclassified in this chart. This error was corrected, resulting in a higher 2022 total of approved load than was previously reported. The overall size of the queue was not impacted by this error.
The data for these outages is submitted by operators of generation assets and is used by ERCOT staff in the operation of the Texas power grid. This report does not contain Resource outages for generators that are no longer operational on the Texas power grid or have not begun operating on the Texas power grid.
Large Load Interconnection Status & Analytics Update
Loads Approved to Energize – Observations. Of the 4,479 MW that have received Approval to Energize, ERCOT has observed a non-simultaneous peak consumption of 2,902 MW. This is calculated as the sum of the maximum value for each individual load regardless of when that maximum occurred. This value represents how …
12,190 5,186 28,749 6,393. April 2022 August 2022. PUBLIC. Current LLI Interconnection Queue. • Chart is cumulative, with 35,142 MW currently being tracked in the queue • The TBD column contains planned projects with no defined target in-service date, as well as remaining MWs after an interim limit has been applied to a proposed …
Interconnection Queue Capacity by Fuel Type. Queue totals: Solar 123 GW (51.2%), Wind 23 GW (9.7%), Gas 12 GW (5.1%), Battery 79 GW (32.9%) (Excludes capacity associated with projects designated as Inactive per Planning Guide Section 5.7.6) A break-out by zone can be found in the monthly Generator Interconnection Status (GIS) …
Current Large Load Interconnection Queue. NOTE: In January 2024 ERCOT identified several projects that had been previously misclassified in this chart. This error was corrected, resulting in a higher 2023 total of approved load than was previously reported. The overall size of the queue was not impacted by this error.
Grid and Market Conditions. These dashboards offer a snapshot of current conditions in the ERCOT system. The timestamp on each indicates when the information was last updated. Click the Full View link on a dashboard for an expanded display. *Note: The 6-Day Forecast graph should only be used as a relative indication of future system conditions.
Interconnection Queue Capacity by Fuel Type Queue totals: Solar 101 GW (53.2%), Wind 22 GW (11.7%), Gas 18 GW (9.7%), Battery 47 GW (24.8%) (Excludes capacity associated with Projects designated as Inactive per Planning Guide Section 5.7.6) A break-out by zone can be found in the monthly Generator Interconnection Status …
The study was complete in May 2022, and the final report was posted on the ERCOT public website. The key findings and conclusions identified from the study are as follows: ‒ Continued increase in oil and gas development is expected within Permian Basin ‒ Future electricity demand associated with oil and gas. 12,000.
Queue totals: Solar 106 GW (53.2%), Wind 21 GW (10.7%), Gas 18 GW (9.2%), Battery 52 GW (26.3%) (Excludes capacity associated with Projects designated as Inactive per Planning Guide Section 5.7.6) A break-out by zone can be found in the monthly Generator Interconnection Status (GIS) reports
Large Load Interconnection Status. LFLTF Meeting January 23, 2023. PUBLIC. ERCOT Activity Since October LFLTF. •New contractor hired to support large load interconnection queue •NPRR, NOGRR, PGRR language drafted •TSP RFI responses received through December 2022. –ERCOT reviewing responses and updating …
Latest ERCOT (Electric Reliability Council of Texas) Interconnection Queue Requests with daily data updates — Interconnection…
Track interconnection queue requests across US ISOs and utilities, with daily data updates. Learn what types of projects are being proposed, where, and how long they take to get approved.
This page provides current information on long-term planning in the ERCOT region. MIS LOG IN. About ERCOT. About ERCOT; Company Profile. ... 2022 - zip - 6.2 MB. 2022 Region Transmission Plan Report Public. Dec 22, 2022 - zip ... ERCOT Permian Basin Load Interconnection Study Report. Dec 8, 2021 - zip ...
Planning Summary. ERCOT is tracking 1,065 active generation interconnection requests totaling 213,604 MW as of June 30. This includes 111,731 MW of solar, 22,243 MW of wind, 65,366 MW of battery, and 12,744 MW of gas projects; 59 projects were categorized as inactive, down from 64 inactive projects in May 2022.
Current LLI Interconnection Queue • Approved to Energize –Projects that have received Approval to Energize from ERCOT Operations. NOTE: not all MWs in this category have